Why Build Your Suite With a Construction Manager
Most laneway and garden suite builders in Toronto sell a fixed-price package. The price looks certain. What you can't see is the margin inside it, what each trade actually costs, or what happened when the soil report came back wrong.
Ashgroup builds suites as construction manager. You get a disclosed fee, agreed in writing before design starts. Every trade — excavation, foundation, framing or CLT panels, mechanical, electrical, finishes — is tendered to at least three bidders and you see every bid. Changes are priced and approved by you before the work happens. When the project finishes under budget, the savings are yours, not ours.
For a $350,000–$500,000 build, that transparency is the difference between knowing what your suite cost and being told what it cost.
It also means you keep your options. Want to use the City's pre-approved plans to save design fees? We'll build to them. Want a custom design from your own architect? We'll coordinate it. Want a mass timber suite that goes up in days instead of weeks? We've done that in Toronto already.

laneway house in toronto

laneway house in toronto

Garden suite in Toronto

laneway house in toronto
Laneway Suite or Garden Suite?
Toronto permits one or the other on a lot, not both. Which one you can build depends on where your lot sits.

Requires
Lot abuts a public laneway
By-law
569-2013 Ch. 150.8 (By-law 810-2018, amended 847-2025)
Storeys
Up to two
Entrance
Faces the lane
Fire Access
Principal entrance within the OBC travel-distance limit from the public street, or a sprinkler alternative
Parking
None required
Landscaping
75% of required rear-yard landscaping must be soft

Requires
Any residential lot with enough rear-yard depth
By-law
569-2013 Ch. 150.7 (By-law 89-2022, amended 849-2025)
Storeys
Up to two, subject to separation and angular plane
Entrance
Via the side yard or a path from the street
Fire Access
Principal entrance within the OBC travel-distance limit from the public street, or a sprinkler alternative
Parking
None required
Landscaping
75% of required rear-yard landscaping must be soft
What's Changed for 2025-2026
The rules have changed twice in the last year. If you read a guide written before late 2025, some parts may be wrong.
Insured Refinancing
Since January 2025, CMHC-insured refinancing can fund a secondary suite on an owner-occupied property. We produce the budget and schedule in the format lenders ask for.
Pre-Approved
Plans
The City published pre-approved laneway and garden suite designs. They cut design time and cost; siting and zoning still get a full review at permitting.
Development Charges
Lots with up to four units are exempt. A laneway or garden suite added as a fifth unit under the City's Development Charges Deferral Program is not counted toward the four, and its charges are deferred for 20 years as long as it stays rental (By-law 650-2025). We set the deferral agreement up as part of the permit package.
Affordable Loans
The City discontinued the forgivable-loan program in January 2026 for lack of provincial funding. Don't budget for it.
Bigger Envelope
By-laws 847-2025 (laneway) and 849-2025 (garden) reduced setbacks, allowed second-storey cantilevers beyond the ground floor, and raised the garden suite floor area cap to 120 m², provided the suite stays smaller than the main house.
Panelised Construction and CLT Advantage
A laneway lot is tight: neighbours on three sides, a lane that can't be blocked for long. That is exactly where cross-laminated timber earns its keep. CLT panels — large solid-wood slabs made from layers of lumber glued at right angles — arrive on site cut to the millimetre, with window and door openings, service chases and connection points already machined. A two-storey suite structure goes up in two to four days with a small crane or a telehandler, and the building is closed in before the weather turns.
What that means for an owner: fewer weeks of trades on site, less disruption to you and your neighbours, and a structure that is the finished wall, floor and ceiling at once. Exposed CLT is warm, quiet and needs no drywall where you choose to leave it visible. Fire and sound performance are well documented under the Ontario Building Code, and Toronto Building has reviewed and approved CLT suites, including ours.
CLT also carries less embodied carbon than a comparable concrete or steel-framed build, and the wood is sourced from Canadian forests. If a lower-carbon home matters to you or to a future buyer, this is the structure that delivers it without a premium finish budget.
Ashgroup has delivered a CLT laneway house in Toronto and CLT custom builds across Ontario. We work directly with Canadian CLT manufacturers on panel design, lead times and delivery sequencing, so the shop drawings, the crane day and the site prep are coordinated as one schedule rather than three. If you want a suite that is faster to build, quieter to live in and carbon-lighter, we can price it against a conventional build and let you compare.
How the Project Runs
01
Eligibility check (free, one week) Zoning review against 569-2013, laneway abutment or rear-yard depth, fire-access path, tree protection, servicing. You get a yes, a no, or a "yes with a variance" and what that costs.
02
Design and budget (6–10 weeks) Pre-approved plan, your architect, or ours. We produce a Class C estimate, a cash-flow schedule, and the DC deferral application alongside the drawings.
03
Tender (3–4 weeks) Trade packages to three or more bidders each. You see every bid and sign every award.
04
Permit (City average 3–4 months in 2026; faster for pre-approved plans) We manage the Toronto Building application, examiner comments, and any Committee of Adjustment hearing.
05
Construction (4–7 months) Weekly site meetings, monthly cost reports, inspections scheduled against the sequence. CLT or panelized structures shorten this phase materially.
06
Occupancy and warranty Final inspections, occupancy, Tarion enrolment where it applies, and the as-built package for your lender and insurer.